Galliford Try (the contractor) are on track to deliver Blocks 1, 2 and 3 as per the schedule with Block 1 in March 2020, Block 2 in July 2020 and Block 3 in September 2020.
Galliford Try have completed the majority of the envelope works, including the lightweight steel frame structure, installation of all windows and roofing works complete and weathered. Brickwork is ongoing to Block 1 between levels 4 – 6. Internally all pods have been positioned and drainage connections made. The first visit for the partitions is complete and first fix of services to level 4 have been completed. Plastering works are ongoing on levels 1 & 2 and kitchens are being installed.
As above, the majority of envelope works in Block 2 have been completed, with brickwork being installed to levels 4 & 5. Partitions have been installed to level 3 allowing for the bathroom pods to be positioned and drainage connections made.
Block 3 is also processing nicely and is following behind Block 2. The lightweight steel frame has now completed and windows are being installed to level 4. Brickwork has commenced between lower ground and first floor. All bathroom pods have been delivered.