Birmingham is transforming rapidly into the proud, vibrant and modern UK’ second city. Just this year, the city has seen brand new grade A offices, the world’s largest retail store, the extension of the tram network, restored historical and cultural heritage sites, and many more exciting changes. With the major investments pouring into the city, the is no wonder Birmingham is becoming a magnet for buy-to-let investors and an attractive choice for people relocating to the lively city centre. To see what has happened in Birmingham over the past year, click here.

Monday, 28 October 2019 / Published in News

Birmingham property market has performed extremely well compared to other regions and the strong demand has driven the prices up. With a fast growing population and one of the highest retention of its students, demand in Birmingham is fast outpacing the supply. To discover more about these trends encompassing all sectors in the property industry, click here.

Sunday, 27 October 2019 / Published in News

The construction at The Axium is progressing well and completion for each block is still on track for March, July and September 2020.

The lightweight steel frame is now complete across all 3 blocks and the brickworks are ongoing.

The internal fit out is taking place throughout and Blocks 1 and 2 and the kitchens are currently being installed throughout block 1.

Block 3 is progressing with window installation taking place, as well as roof and brick works.

We are also pleased to announce that the show homes are now officially open and available to view.

Saturday, 28 September 2019 / Published in News

Galliford Try (the contractor) are on track to deliver Blocks 1, 2 and 3 as per the schedule with Block 1 in March 2020, Block 2 in July 2020 and Block 3 in September 2020.

Galliford Try have completed the majority of the envelope works, including the lightweight steel frame structure, installation of all windows and roofing works complete and weathered. Brickwork is ongoing to Block 1 between levels 4 – 6. Internally all pods have been positioned and drainage connections made. The first visit for the partitions is complete and first fix of services to level 4 have been completed. Plastering works are ongoing on levels 1 & 2 and kitchens are being installed.

As above, the majority of envelope works in Block 2 have been completed, with brickwork being installed to levels 4 & 5. Partitions have been installed to level 3 allowing for the bathroom pods to be positioned and drainage connections made.

Block 3 is also processing nicely and is following behind Block 2. The lightweight steel frame has now completed and windows are being installed to level 4. Brickwork has commenced between lower ground and first floor. All bathroom pods have been delivered.


Virtual visit of the show homes.

Discover your new apartment

Beautifully designed to fit into any world

TOP
Get in touch here

Contact Form

For more details, please contact our sales team on:
+44 121 796 0171




    By submitting this form, you confirm you are happy for Court Living (appointed agency for Top Capital Group) to process your information and for a member of the sales team to make contact with you to discuss your enquiry.

    All the details on how your data will be used, can be found here; You can change your marketing preferences at anytime by emailing Court Living directly at living@courtcollaboration.com or by speaking to a Court Living representative.”