Birmingham is transforming rapidly into the proud, vibrant and modern UK’ second city. Just this year, the city has seen brand new grade A offices, the world’s largest retail store, the extension of the tram network, restored historical and cultural heritage sites, and many more exciting changes. With the major investments pouring into the city, the is no wonder Birmingham is becoming a magnet for buy-to-let investors and an attractive choice for people relocating to the lively city centre. To see what has happened in Birmingham over the past year, click here.
Birmingham property market has performed extremely well compared to other regions and the strong demand has driven the prices up. With a fast growing population and one of the highest retention of its students, demand in Birmingham is fast outpacing the supply. To discover more about these trends encompassing all sectors in the property industry, click here.
The construction at The Axium is progressing well and completion for each block is still on track for March, July and September 2020.
The lightweight steel frame is now complete across all 3 blocks and the brickworks are ongoing.
The internal fit out is taking place throughout and Blocks 1 and 2 and the kitchens are currently being installed throughout block 1.
Block 3 is progressing with window installation taking place, as well as roof and brick works.
We are also pleased to announce that the show homes are now officially open and available to view.
Galliford Try (the contractor) are on track to deliver Blocks 1, 2 and 3 as per the schedule with Block 1 in March 2020, Block 2 in July 2020 and Block 3 in September 2020.
Galliford Try have completed the majority of the envelope works, including the lightweight steel frame structure, installation of all windows and roofing works complete and weathered. Brickwork is ongoing to Block 1 between levels 4 – 6. Internally all pods have been positioned and drainage connections made. The first visit for the partitions is complete and first fix of services to level 4 have been completed. Plastering works are ongoing on levels 1 & 2 and kitchens are being installed.
As above, the majority of envelope works in Block 2 have been completed, with brickwork being installed to levels 4 & 5. Partitions have been installed to level 3 allowing for the bathroom pods to be positioned and drainage connections made.
Block 3 is also processing nicely and is following behind Block 2. The lightweight steel frame has now completed and windows are being installed to level 4. Brickwork has commenced between lower ground and first floor. All bathroom pods have been delivered.
中文查詢熱線 WhatsApp: +852 6394 6792
中文查詢電郵: info@topcapgroup.com.com
Tel: +01217960166 Email: living@courtcollaboration.com
Address: The Axium, Windmill St, Birmingham B1 1NS
Notice: Concierge operate 7 days a week from 7am – 7pm. Their email address is: theaxiumconcierge@centrick.co.
For more details, please contact our sales team on:
+44 121 796 0171